Pipe fall calculator

Convert a measured pipe run and entered ratio into the required vertical drop between two datum points. You enter the ratio from your design or guidance; the page shows the arithmetic.

Planning arithmetic · Metric units
Worked example only: JavaScript is unavailable, so the editable fields below are not live. The fixed example uses 12 m at 1:80 and gives 150 mm drop.
metres
Measure along the planned horizontal route.
ratio
Type the second number only, e.g. 80 for 1 in 80.
mm
Kept on the record only; it does not change the drop.
step
Formula: vertical drop (mm) = run (m) × 1,000 ÷ entered ratio. Full precision is retained internally and rounded only for display.
Worked example · Default entered values
150mm

Across 12 m at 1:80, the outlet datum is 150 mm below the inlet datum when recorded to the nearest 5 mm.

1.25%Calculated gradient
110 mmYour nominal diameter
Inputs and assumptions

Entered values: 12 m measured run · 1:80 ratio · 110 mm nominal diameter · 5 mm recording step. The formula calculates geometric fall only; it does not establish design compliance, invert levels or connection permission.

Method

Before choosing a method, use the Welsh responsibility and measured-level guide to identify the next responsible body and keep one datum through the worked invert-level example. This resource does not select a design ratio or provide emergency contractor services.

The calculation uses transparent arithmetic over the values you enter. For a 12 metre run at a ratio of 1 in 80, the unrounded drop is 12 × 1,000 ÷ 80 = 150 mm. Take the ratio from your design, the relevant guidance or a competent person.

What to measure

A calculated invert drop is not excavation depth: ground levels, external pipe geometry and bedding are separate. After design and services checks, use a designed average depth in the trench quantities worksheet, not the fall figure.

Record the start and end points, the planned route length and the intended connection point.

Where levels and the route need to be measured on site, compare surveying equipment hire after deciding which instruments and accuracy the job requires.

Do not treat the number as permission to excavate or connect. Existing invert levels, buried services, route ownership, access, ground stability and connection requirements sit outside this calculation.

Worked example

InputExample value
Measured run12 m
Entered ratio1:80
Arithmetic12 × 1,000 ÷ 80
Unrounded result150 mm

Sources

The arithmetic is elementary and cites no source. The safety limits around it come from official guidance listed in the sources. See the full methodology.

Blank field worksheet

Job/reference
Date
Start datum
End datum
Measured run (m)
Entered ratio (1:n)
Nominal diameter (mm)
Recording step (mm)
Unrounded drop (mm)
Recorded drop (mm)
Checked by

Calculated the fall? Scope the trench next.